Time and work is about rates. Add the rates of people working together, never their days.

  • Unlimitedअसीमित fresh questionsनए प्रश्न
  • Answersउत्तर always one tap awayहमेशा एक टैप दूर
  • 3 subtopicsउप-टॉपिक
  • SSC CGL ~1
  • IBPS PO ~1
  • TCS NQT ~2

Practice questions are in English for now.अभ्यास के प्रश्न अभी अंग्रेज़ी में हैं।

How time and work worksसमय और कार्य को समझिए

Take the total work as the LCM of the given days. Then each person’s efficiency is a whole number of units per day, and everything else is simple division.

People working together add their efficiencies. Someone who undoes work (like a leak) has a negative efficiency.

When more people, days or hours are involved, use the M × D × H relation: more people need fewer days for the same work.

Tricks that save timeसमय बचाने वाली ट्रिक्स

All tricks →सभी ट्रिक्स →

Each trick says when to use it, why it works and when it fails. Formula tricks are checked by code over their whole range.हर ट्रिक बताती है कि उसे कब इस्तेमाल करें, वह क्यों काम करती है और कब नहीं। सूत्र वाली ट्रिक्स को कोड से उनकी पूरी रेंज पर जाँचा गया है।

Mental mathsमानसिक गणितRarely taughtकम सिखाई जाने वाली✓ Checked on 841 cases✓ 841 मामलों पर जाँची गई

Work as a percentage per day

Use it when:कब इस्तेमाल करें: Two or three people (or pipes) working together, with days such as 8, 12, 16 or 20 that turn into friendly percentages.

  1. Each person does 100/days % a day: 8 days → 12.5%, 10 → 10%, 12 → 8.33%, 20 → 5%.
  2. Add the percentages (subtract for a leak), then days = 100 ÷ total.
Exampleउदाहरण

A: 10 days, B: 8 days. Together?

→ 10% + 12.5% = 22.5% a day → 100/22.5 = 4 4/9 days

Why it works, and when it failsयह क्यों काम करती है, और कब नहीं

Why:क्यों: It is the LCM method with the total work fixed at 100 units, so the fraction table you already know does the work.

Limits:सीमाएँ: Messy for days like 7 or 13 (14.28%, 7.69%): there the LCM method is cleaner.

Formulaसूत्र✓ Checked on 780 cases✓ 780 मामलों पर जाँची गई

Find one worker from “together” time

Use it when:कब इस्तेमाल करें: “A and B together take t days; A alone takes a days. How long does B take alone?”

  1. B = a × t / (a − t).
Exampleउदाहरण

Together 6 days, A alone 10 days

→ B = 60/4 = 15 days

Why it works, and when it failsयह क्यों काम करती है, और कब नहीं

Why:क्यों: 1/B = 1/t − 1/a = (a − t)/(a t).

Limits:सीमाएँ: a must be greater than t (one person alone is always slower than the pair).

Solved examplesहल किए गए उदाहरण

Answers and full solutions are shown. Hide them to test yourself first.उत्तर और पूरे हल दिखाए गए हैं। पहले खुद को परखने के लिए इन्हें छिपाइए।

  1. Example 1उदाहरण 1 · Time and work: two people together · Easyआसान

    Arjun can paint a house in 24 days and Meera can paint it in 12 days. Working together, in how many days will they finish it?

    1. 6 days
    2. 7 days
    3. 8 days
    4. 10 days
    Answer:उत्तर: 8 days
    1. Total work = 24 units.
    2. Together per day = 1 + 2 = 3 units.
    3. Days = 24 ÷ 3 = 8.
  2. Example 2उदाहरण 2 · Two people working on alternate days · Easyआसान

    A can do a piece of work in 5 days and B in 10 days. They work on alternate days, A starting. In how many days is the work finished?

    1. 6 1/2 days
    2. 3 1/3 days
    3. 7 days
    4. 6 2/3 days
    Answer:उत्तर: 6 1/2 days
    1. Total work = 10 units; A = 2/day, B = 1/day; a two-day cycle = 3 units.
    2. 3 full cycles (6 days) do 9 units, leaving 1.
    3. A works next and the rest is finished on the following day(s): total 6 1/2 days.
  3. Example 3उदाहरण 3 · Men, days, hours and work (chain rule) · Easyआसान

    6 workers, working 10 hours a day, finish the wall in 15 days. How many days will 10 workers take to finish the wall, working 10 hours a day?

    1. 9 days
    2. 10 days
    3. 25 days
    4. 11 days
    Answer:उत्तर: 9 days
    1. M₁D₁H₁/W₁ = 6 × 15 × 10 / 1 = 900 worker-hours per unit.
    2. D₂ = 6 × 15 × 10 × 1 / (10 × 10 × 1).
    3. D₂ = 900 / 100 = 9 days.
  4. Example 4उदाहरण 4 · Time and work: two people together · Mediumमध्यम

    Aditya and Isha together can complete a project in 14 days. Aditya alone can complete it in 21 days. In how many days can Isha alone complete it?

    1. 34 days
    2. 38 days
    3. 42 days
    4. 53 days
    Answer:उत्तर: 42 days
    1. Work = 42 units. Together = 3/day, Aditya = 2/day.
    2. Isha = 1 units/day.
    3. Isha alone = 42 ÷ 1 = 42 days.
  5. Example 5उदाहरण 5 · Two people working on alternate days · Mediumमध्यम

    A can do a piece of work in 12 days and B in 14 days. They work on alternate days, A starting. In how many days is the work finished?

    1. 6 6/13 days
    2. 13 days
    3. 12 12/13 days
    4. 12 6/7 days
    Answer:उत्तर: 12 6/7 days
    1. Total work = 84 units; A = 7/day, B = 6/day; a two-day cycle = 13 units.
    2. 6 full cycles (12 days) do 78 units, leaving 6.
    3. A works next and the rest is finished on the following day(s): total 12 6/7 days.
  6. Example 6उदाहरण 6 · Men, days, hours and work (chain rule) · Mediumमध्यम

    24 workers, working 10 hours a day, finish 2 km of building in 20 days. How many days will 16 workers take to finish 2 km of building, working 6 hours a day?

    1. 13.33 days
    2. 51 days
    3. 50 days
    4. 30 days
    Answer:उत्तर: 50 days
    1. M₁D₁H₁/W₁ = 24 × 20 × 10 / 2 = 2,400 worker-hours per unit.
    2. D₂ = 24 × 20 × 10 × 2 / (16 × 6 × 2).
    3. D₂ = 9,600 / 192 = 50 days.
  7. Example 7उदाहरण 7 · Time and work: two people together · Hardकठिन

    Rohan can complete a piece of work in 10 days and Diya in 10 days. They work together for 2 days, then Rohan leaves. In how many more days will Diya finish the remaining work?

    1. 5 days
    2. 6 days
    3. 7 days
    4. 8 days
    Answer:उत्तर: 6 days
    1. Work = 10 units; Rohan = 1/day, Diya = 1/day.
    2. Together for 2 day(s): 4 units. Left: 6 units.
    3. Diya needs 6 ÷ 1 = 6 days.
  8. Example 8उदाहरण 8 · Two people working on alternate days · Hardकठिन

    A can do a piece of work in 12 days and B in 13 days. They work on alternate days, B starting. In how many days is the work finished?

    1. 12 12/25 days
    2. 6 6/25 days
    3. 12 6/13 days
    4. 12 1/2 days
    Answer:उत्तर: 12 1/2 days
    1. Total work = 156 units; A = 13/day, B = 12/day; a two-day cycle = 25 units.
    2. 6 full cycles (12 days) do 150 units, leaving 6.
    3. B works next and the rest is finished on the following day(s): total 12 1/2 days.

Common mistakesआम गलतियाँ

  • Adding the days instead of the rates.
  • Forgetting that one person leaves partway through the job.

Frequently asked questionsअक्सर पूछे जाने वाले प्रश्न

What is the fastest method for time and work?

The LCM method: take total work = LCM of the days and work with whole-number efficiencies.

If A takes 10 days and B takes 15 days, how long together?

Total work 30 units; A does 3, B does 2, together 5 units a day, so 6 days.

How are pipes and cisterns related?

They are the same idea: filling pipes add, emptying pipes subtract.