CA INTERMEDIATE: COSTING & FM · OVERHEADS: ABSORPTION COSTING

Overhead absorption rate and under/over-absorption

Absorption rate = Budgeted overheads ÷ Budgeted base (machine hours, labour hours or labour cost). Absorbed = rate × actual base; absorbed > actual → over-absorbed.

Loading practice…

Worked examples

Example 1 · level 1

Gupta Auto Parts budgets factory overheads of ₹21,75,000 and 25,000 machine hours for the year. Find the machine hour rate.

Show solution
  1. Machine hour rate = ₹21,75,000 ÷ 25,000 = ₹87 per hour.

Answer: ₹87

Example 2 · level 2

Joshi Pharma Ltd budgets overheads of ₹67,500 and direct labour cost of ₹1,35,000. Overheads are absorbed as a % of direct labour cost. Job No. 543 has direct labour of ₹5,200. How much overhead is charged to the job?

Show solution
  1. Rate = ₹67,500 ÷ ₹1,35,000 × 100 = 50%.
  2. Overhead on job = 50% × ₹5,200 = ₹2,600.

Answer: ₹2,600

Example 3 · level 3

Nair Spices Pvt Ltd set a machine hour rate of ₹73 (budget: ₹13,14,000 for 18,000 hours). Actual: 19,750 machine hours worked and actual overheads ₹13,08,500. What is the position?

  1. Under-absorbed by ₹1,33,250
  2. Over-absorbed by ₹1,33,250
  3. Under-absorbed by ₹5,500
  4. Over-absorbed by ₹5,500
Show solution
  1. Absorbed = ₹73 × 19,750 = ₹14,41,750.
  2. Actual = ₹13,08,500.
  3. Over-absorbed by ₹1,33,250.

Answer: Over-absorbed by ₹1,33,250