Worked examples
Example 1 · level 1
Sharma Industries Ltd: project cost ₹5,40,000, no salvage, life 3 years. Profits after depreciation and tax: ₹81,500, ₹82,000, ₹79,500. Find ARR on initial investment (%), two decimals.
Show solution
- Average profit = ₹81,000.
- Initial investment = ₹5,40,000.
- ARR = 81,000 ÷ 5,40,000 × 100 = 15%.
Answer: 15 %
Example 2 · level 2
Iyer Foods Ltd: project cost ₹6,10,000, salvage value ₹20,000, life 3 years. Profits after depreciation and tax: ₹74,000, ₹73,500, ₹71,500. Find ARR on average investment (%), two decimals.
Show solution
- Average profit = ₹73,000.
- Average investment = (₹6,10,000 + ₹20,000) ÷ 2 = ₹3,15,000.
- ARR = 73,000 ÷ 3,15,000 × 100 = 23.17%.
Answer: 23.17 %
Example 3 · level 3
Iyer Foods Ltd: project cost ₹5,90,000, salvage value ₹20,000, life 4 years. Profits after depreciation and tax: ₹1,19,000, ₹1,17,500, ₹1,19,000, ₹1,16,500. Find ARR on average investment (%), two decimals.
Show solution
- Average profit = ₹1,18,000.
- Average investment = (₹5,90,000 + ₹20,000) ÷ 2 = ₹3,05,000.
- ARR = 1,18,000 ÷ 3,05,000 × 100 = 38.69%.
Answer: 38.69 %