Example 1 · level 1
Kapoor Electricals — Standard hours for actual output 1,850 @ ₹110/hour. Actual hours worked and paid 1,690 @ ₹130/hour (no idle time). Find the labour rate variance.
- ₹37,000 (A)
- ₹33,800 (F)
- ₹33,800 (A)
- ₹37,000 (F)
Show solution
- LRV = (110 − 130) × 1,690 = -33,800 → ₹33,800 (A).
Answer: ₹33,800 (A)